CostPerCover

Exam Prep app CSLB Law & Business

Practice questions with explained answers

CSLB Law and Business practice test

300 practice questions, each with an explanation of why the right answer is right and where the rule comes from. Try 10 of them below; the rest are in the CostPerCover Exam Prep app for iPhone, iPad and Android.

Download on the App Store Get it on Google Play

Free sample of every test. Unlocking the full test is a one-time purchase ($19.99 in the U.S.), with no subscription.

Try 10 questions

Pick your answer first, then open the answer to see why.

Question 1 · Business Organization and Licensing

A contractor takes a deposit for the Smith job and uses it to buy materials for the Jones job. What is this?

  1. Normal cash-flow management, provided both jobs finish
  2. Diversion of funds, a cause for disciplinary action
  3. Permitted if the contractor keeps a written record
  4. A violation only if the Smith job is not completed
Show the answer

Answer: B. Diversion of funds, a cause for disciplinary action

Diversion of funds received for a specific project is a cause for disciplinary action, and so is failing to substantially account for how those funds were used. Completing both jobs later does not cure it. This is why job-specific accounting is not merely good bookkeeping - it is a license matter.

From the source“Diversion of funds or property received for prosecution or completion of a specific construction project or operation, or for a specified purpose in the prosecution or completion of any construction project or operation, or failure substantially to account for the application or use of such funds or property”

Source: B&P section 7108

Question 2 · Business Finances

The company cannot pay. On whom may the IRS impose the trust fund recovery penalty?

  1. Only on the corporation itself
  2. On any shareholder, in proportion to their holding
  3. On persons responsible for collecting or paying over the taxes who acted willfully
  4. On the company's outside accountant
Show the answer

Answer: C. On persons responsible for collecting or paying over the taxes who acted willfully

Responsibility plus willfulness, not ownership. A bookkeeper who chose which bills to pay can be liable; a passive shareholder is not. Incorporating does not put this one behind the corporate veil, which is the point candidates most often get wrong.

From the source“the trust fund recovery penalty may be imposed on all persons who are determined by the IRS to be responsible for collecting, accounting for, or paying over these taxes, and who acted willfully in not doing so.”

Source: IRS Publication 15 (2026), section 11

Question 3 · Employment Requirements

What determines how often an employer's payroll deposits are made to the IRS?

  1. The amount of payroll liability
  2. The number of employees on the payroll
  3. How long the company has been in business
  4. The ratio of salaried employees to hourly employees
Show the answer

Answer: A. The amount of payroll liability

The size of the payroll tax liability, measured over a lookback period, puts an employer on a monthly or semiweekly deposit schedule. Headcount does not decide it: ten low-paid part-timers can deposit less often than two highly paid staff. This is CSLB's own published sample question, reproduced with its published answer.

From the source“What determines how often an employer's payroll deposits are made to the IRS? a. The amount of payroll liability*”

Source: CSLB Law and Business Study Guide, sample question 1

Question 4 · Insurance and Liens

A subcontractor was hired by the direct contractor, not by the owner. Is their work "authorized" for lien purposes?

  1. No, only work requested by the owner is authorized
  2. Yes, work provided or authorized by a direct contractor is authorized
  3. Only if the owner countersigned the subcontract
  4. Only if the subcontractor served a preliminary notice first
Show the answer

Answer: B. Yes, work provided or authorized by a direct contractor is authorized

Authorized either at the owner's request or through a direct contractor, subcontractor, architect, project manager or other person with authority. This is why an owner can end up facing a lien from someone they never met and never hired — the authorization ran down the chain, not to them.

From the source“It is provided or authorized by a direct contractor, subcontractor, architect, project manager, or other person having”

Source: Civil Code section 8404(b)

Question 5 · Contract Requirements and Execution

In which of these situations is the Three-Day or Five-Day Right to Cancel notice NOT required in a home improvement contract?

  1. The buyer is a senior citizen
  2. The contract was negotiated at the contractor's place of business
  3. The contract is under $1,000
  4. The buyer has used the same contractor before
Show the answer

Answer: B. The contract was negotiated at the contractor's place of business

The notice is not required when the contract is negotiated at the contractor's place of business - the right to cancel exists because of doorstep selling. The other exclusions are the Seven-Day Right to Cancel contracts and certain Alarm Company Act contracts. Contract size is irrelevant.

From the source“shall be provided to the buyer unless the contract is: (i) Negotiated at the contractor's place of business.”

Source: B&P section 7159(a)(6)(A)(i)

Question 6 · Public Works

What must a contractor have before bidding on or performing a public works contract?

  1. A performance bond on file with the awarding body
  2. Current registration and qualification to perform public work under section 1725.5
  3. A C-license in the relevant trade
  4. Five years of documented public works experience
Show the answer

Answer: B. Current registration and qualification to perform public work under section 1725.5

DIR registration under 1725.5, and it must be current before you bid, before you are listed in someone else's bid, and before you perform. Three separate moments, all barred to an unregistered contractor.

From the source“shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work”

Source: Labor Code section 1771.1(a)

Question 7 · Safety

Beyond specific required devices, what general duty does Labor Code section 6401 place on every employer?

  1. To carry an excess liability policy
  2. To do every other thing reasonably necessary to protect the life, safety, and health of employees
  3. To employ a full-time safety officer
  4. To inspect the site weekly
Show the answer

Answer: B. To do every other thing reasonably necessary to protect the life, safety, and health of employees

The catch-all general duty. Complying with every specific regulation is not a defense if something obvious and reasonably preventable was left undone — which is how Cal/OSHA cites hazards no numbered order happens to cover.

From the source“Every employer shall do every other thing reasonably necessary to protect the life, safety, and health of employees.”

Source: Labor Code section 6401

Question 8 · Business Organization and Licensing

Which of the following is expressly listed in section 7110 as a body of law whose willful violation is a cause for disciplinary action?

  1. The Vehicle Code
  2. The safety laws, labor laws, compensation insurance laws and Unemployment Insurance Code
  3. The Uniform Commercial Code
  4. Local sign ordinances
Show the answer

Answer: B. The safety laws, labor laws, compensation insurance laws and Unemployment Insurance Code

Section 7110 pulls safety, labor, workers' compensation and unemployment insurance law into the license law. A Cal/OSHA citation or an unpaid workers' comp premium is therefore not just its own problem - it is a route to losing the license.

From the source“The safety laws or labor laws or compensation insurance laws or Unemployment Insurance Code of the state.”

Source: B&P section 7110(c)

Question 9 · Business Organization and Licensing

Within what period must a complaint about a LATENT act or omission concerning structural defects be filed with CSLB?

  1. Two years
  2. Four years
  3. Ten years
  4. There is no limit
Show the answer

Answer: C. Ten years

Ten years for a latent structural defect; four years for a patent act or omission. Patent means apparent on reasonable inspection, latent means hidden. The two numbers sit in the same sentence of the notice the contractor is required to print, which is why the exam likes them.

From the source“A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the alleged violation.”

Source: B&P section 7030(a)

Question 10 · Business Finances

What is the California State Disability Insurance withholding rate for 2026?

  1. 0.9 percent
  2. 1.1 percent
  3. 1.2 percent
  4. 1.3 percent
Show the answer

Answer: D. 1.3 percent

1.3 percent for 2026. This rate has moved every year recently — 0.9 percent in 2023, 1.1 in 2024, 1.2 in 2025 — so it is a figure to look up rather than remember. All three older rates are on the same EDD page and all three are plausible-looking wrong answers.

From the source“The SDI withholding rate for 2026 is 1.3 percent.”

Source: EDD, Contribution Rates and Withholding Schedules (2026)

The test at a glance

CSLB Law and Business Exam (California contractors)

Questions in the app
300
Questions in a practice simulation
115
Time
210 minutes
The app’s practice target
75%
Current to
California law current to January 1, 2026

Topics and their share of the test

Keep practicing in the app

Free sample of every test. Unlocking the full test is a one-time purchase ($19.99 in the U.S.), with no subscription.

Where the questions come from

Independent practice questions. Not affiliated with or endorsed by the Contractors State License Board (CSLB), PSI or any government agency. The questions are our own practice questions, not questions from the real test.

Other tests in the app